Good week from the team. Framing coming along well both downstairs in the AWA Tenancy and upstairs in the Early Learning Childhood Centre. These last few days we have been preparing the compartmentation walls (smoke walls) up high on the scaffolding and scissor lift. Looking to sheet these walls in the Atrium area, get them troweled, sanded and painted so can remove flooring underneath to installed Glazed Framed Windows. #progress #healthhub #philthecracks #launcestonplasterer
fyrcheck
Health Hub Taking Shape
Steel Walls are well under way and the new Early Learning Centre at the Launceston Health Hub is taking shape. #healthhub #steelstudwalls #philthecracks
Health Hub Progress
Great week from the team. Construction meeting was held and the best plan of attack for this project was determined. Ceilings are well underway and the first room among many has been framed. Great effort men, looking forward to next weeks challenges. #healthhub #medhub #philthecracks #progress
Plastering A Skylight
Now this is a skylight. Over 2 metres deep and 1800 wide. Used a special scissor lift to access this space to sheet and trowel. #skylights #hobartplasterer #tasmania
Stages of Firewall Construction
1: Remove Old Ceiling
2: Frame up Firerated wall above Ceiling:
3: Re-Sheet Fyrcheck Plasterboard Ceiling:
4: Replace Existing Timber Beads:
5: Trowel Joins and Screw Holes.
6: Paint it and your Done.
Thats one side of the 2 adjoining units and currently we are performing the exact same steps on the otherside in unit 2.
You are required to install firewall according to Australian Safety Standards and get Council to inspect wall and sign off before you finish.
Regards
Phil