MedHub Plastering Finished

What a busy last month the Phil The Crack Team has had. As of tomorrow the 12/4/19 the MedHub will be officially due to be handed over to the clients. Would like to thank my team and the team from VOS, lead by Andrew Brumby and David Reid, for a pleasant work environment and professionalism that is second to none. Great achievement by all and was a privilege to work on this site. #teameffort #handover

Plastering A Skylight

Now this is a skylight. Over 2 metres deep and 1800 wide. Used a special scissor lift to access this space to sheet and trowel. #skylights #hobartplasterer #tasmania

http://www.philthecracks.com

Stages of Firewall Construction

1: Remove Old Ceiling

scamander fire rated linings

 

2: Frame up Firerated wall above Ceiling:

the one i want to use

3: Re-Sheet Fyrcheck Plasterboard Ceiling:

IMG_3371

4: Replace Existing Timber Beads:

IMG_3375

 

5: Trowel Joins and Screw Holes.

IMG_3383

 

6: Paint it and your Done.

IMG_3398

 

Thats one side of the 2 adjoining units and currently we are performing the exact same steps on the otherside in unit 2.

You are required to install firewall according to Australian Safety Standards and get Council to inspect wall and sign off before you finish.

Regards

Phil